Government’s responsibility towards investor’s loss in toll development on PPP agreements due to delay in land acquisitions

Dena Zahra Aulia, An-An Chandrawulan, Purnama Trisnamansyah

Abstract


Until now, the slow process of land acquisition in toll road infrastructure development projects is still one of the obstacles to the completion of a infrastructure development project. The delay in the land acquisition process is detrimental to parties involved in PPP, especially investors. This study uses a normative juridical approach with analytical descriptive research specifications. Data collection techniques are carried out by means of literature study to obtain secondary data and interviews to obtain primary data, then the data obtained is  analyzed using qualitative juridical methods, namely by taking inventory, systematically arranging, connecting with each other related to the problems studied with the enactment of the provisions of the regulations. one does not conflict with other regulations. The result of this research is a form of responsibility from the Government due to delays in land acquisition, namely compensation in the form of extension of the concession period on a toll road project with a PPP scheme, and consideration of additional initial tariffs on toll roads based on inflation, capital, construction time and increase. the concession period and also the imposition of fines in a business contract, and the last resort for resolving disputes over the PPP agreement through non-litigation or arbitration institutions based on Presidential Regulation Number 38 of 2015.

How to cite item: Aulia, D. Z., Chandrawulan, AA., Trisnamansyah P. (2021). Government’s responsibility towards investor’s loss in toll development on PPP agreements due to delay in landa cquisitions. Jurnal Cakrawala Hukum, 12(1), 21-31.doi:10.26905/idjch.v12i1. 4337.


Keywords


Infrastructure; Toll Road; PPP; Land Procurement; Investors.

Full Text:

PDF

References


Abdulkadir, Muhammad. 2000. Hukum Perdata Indone- sia. Citra Aditya Bakti. Bandung.

Commercial Court of Surabaya with case number 22 / Pdt.Sus-Pailit /2019/PN Sub.

Commission 5 of The House of Representatives of The Republic of Indonesia. 2020. http://dpr.go.id/ accessed on 11th of March.

Darmawan, Yudhi. 2012. Dampak Ketidak Pastian Waktu Pembebasan Tanah Terhadap Besaran Tarif Awal Pada Proyek Investasi Jalan Tol. Universitas Indonesia Digital Library. Depok.

Friana, Hendra. 2020. https://tirto.id/penggarap- proyek-spam-umbulan-terlilit-utang-dan- terancam-pailit-ejMp, accessed on 11th of March 2020.

Harahap, M. Yahya. 1986. Segi-Segi Hukum Perjanjian.

Alumni. Bandung.

Haryanto, F. Kristifiani. 2019. Pemindahan Rumah Ibadah Dan Fasilitas Umum Akibat Pengadaan Tanah Untuk Pembangunan Jalan Tol Berdasarkan Undang - Undang Nomor 2 Tahun 2012 Tentang Pengadaan Tanah Bagi Pembangunan Untuk Kepentingan Umum, Jurnal Hukum Adigama. p. 5.

Herlinda, Erna. 2004. Peranan Pemerintah Atas Tanah Dalam Rangka Pembangunan. Fakultas Hukum Universitas Sumatera Utara: USU Digital Library,

p. 2. Sumatera Utara.

Hermawan, Rudy. 2020. Kaji Ulang Penentuan Tarif dan Sistem Penggolongan Kendaraan Jalan Tol di In- donesia. Jurnal Teknik Sipil: Jurnal Teoretis dan Terapan Bidang Rekayasa Sipil.

Irwin, Timothy & Mokdad, Tanya. 2010. Managing Con- tingent Liabilities in Public Private Partnerships: Prac- tice in Australia, Chile, and South Africa. World Bank Report 101491. Januari 2010. p. vii.

Law No. 2 of 2012 Concerning Land Procurement for Devel- opment in the Public Interest.

Law No. 30 of 1999 Concerning Arbitration and Alternative Dispute Resolution.

National Civil Law of the Indonesian Republic. Presidential Regulation Number 38 of 2015 Concerning

Cooperation of The Government and Business Entities

In Infrastructure Provision.

Presidential Regulation Number 71 of 2012 Concerning Provision of Land Procurement for Development in Interests General and / or other related regulations.

Raharjo, Dwi Bowo. 2020. https://www.suara.com/ac- cessed on 11th of March.

Redaksi Banten Headline. 2020. https://bantenheadline.com/ minim-progres-pemkab-pandeglang-dinilai-lambat-tindak-lanjut-program-nasional/ Ac- cessed on 11th of March 2020.

Republic of Indonesia. 2018. Public-Private Partnerships: Infrastructure Projects Plan in Indonesia. Journal BAPPENAS. Ministry of National Development Planning/ National Development Planning Agency. pp. vi.

Slamet, Sri Redjeki. 2013. Tuntutan Ganti Rugi Dalam Perbuatan Melawan Hukum: Suatu Perbandingan Dengan Wanprestasi, Jurnal Lex Jurnalica. Volume 10 Nomor 2, Agustus, hlm. 114.

Sofwan. & Soedewi, Sri. 1982. Hukum Perjanjian. Univer- sitas Gadjah Mada. Yogyakarta.

Subekti. 2003. Pokok-Pokok Hukum Perdata. Cetakan ke-31. Intermasa. Jakarta.

Sumedang District Court, Case No. 3 / PDT.G / 2017PN.Smd.

Sumedang Religious Court, Case No. 156 / Pdt.P / 2013/ PA Smd.

The World Bank. 2020. https://www.worldbank.org/ en/country /indonesia/ overview, accessed on 4th of January 2020.




DOI: https://doi.org/10.26905/idjch.v12i1.4337

Refbacks

  • There are currently no refbacks.




Copyright (c) 2021 Jurnal Cakrawala Hukum

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.



Publisher: 
Faculty of Law - University of Merdeka Malang
Faculty of Law Building, Terusan Dieng Street 62-64
Malang City, East Java, Indonesia, 65146.

  

Other Link 

Follow Us
See the source image@jurnalcakrawalahukum
See related image detail@Jcakrawalahukum
[email protected]
Phone (0341) 580161
Free Round Icons Png Png Transparent Images - PikPng
Faks (0341) 588395
View JCH Visitors
web statistics

Jurnal Cakrawala Hukum Creative Commons License This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.